MENA Water Review · Visual story

Reducing Non-Revenue Water Could Provide MENA With New Water

In the most water-scarce region on earth, between a quarter and a half of the water put into city networks in several countries earns no revenue. How utilities locate these losses, and why so much of the water remains lost.

Jordan’s largest untapped water source lies in its own pipes.

Jordan has about sixty cubic metres of internal renewable water per person per year. Hydrologists use the phrase absolute scarcity below five hundred cubic metres per person per year. Jordan has signed a 30-year concession for a desalination plant on the Red Sea, an investment of around EUR 4 billion according to SUEZ, with a pipeline of about 438 kilometres north to Amman, according to the project’s 2025 environmental assessment.

There is another way to look at Jordan’s water shortage. In 2022 roughly half the water it put into its municipal networks earned no revenue: about 260 million cubic metres, according to official figures from its Central NRW Unit. In August 2026 the water minister reported the national rate down to 41 per cent. The 2022 volume is close to the 300 million cubic metres a year that the Aqaba to Amman desalination and conveyance project is designed to deliver. The physical part of that loss is water already inside the country, already treated, already pressurised and already paid for.

Jordan is an extreme case, but it is not an outlier. Lebanon’s own water strategy puts non-revenue water at about half of supply. Algeria lost some 40% in distribution in 2004. Saudi Arabia’s ministry put water losses at 33% in 2025. One estimate puts losses in Tunisia’s drinking-water networks at about a quarter, and the World Bank estimates physical losses in Morocco’s distribution networks at around 24%. The region that has invested more heavily than anywhere on earth in making water from the sea is also losing a very large share of that water between the treatment plant and the tap.

50%of Lebanon’s water earns no revenue, the national estimate in its 2024 to 2035 water strategy
~260 mcmJordan’s non-revenue water in 2022, most of what its planned Red Sea project would deliver
346 mm³lost worldwide every day, in Liemberger and Wyatt’s 2019 estimate
$39bnannual value of that water, at only $0.31 a cubic metre
4.4%Dubai’s reported network loss in 2025
40%lost in Algeria’s distribution networks in 2004, World Bank

Half the problem lies not in the pipes but in the ledger.

The technical term is non-revenue water, and the distinction it makes is more important than it may sound. Non-revenue water is not the same as leakage. It is the difference between the volume of water a utility puts into its network and the volume it bills to customers. The losses divide into two different problems, each requiring a different solution.

Real losses are physical. Water escapes through cracked mains, corroded service connections, failed joints and overflowing reservoirs. Most of the water lost this way comes from leaks that never rise to the surface. A service pipe that is leaking into gravel beneath a road can continue doing so for years without anyone above ground noticing. This is the part that engineers can address with valves, sensors and excavators.

Apparent losses are commercial. The water reaches somebody’s tap, but the money does not reach the utility. Meters under-register, especially at low flows and as they age. Some connections have no meter at all. Bills may be estimated, mis-read or assigned to the wrong account; bills that are issued but not collected are a separate collection issue. Replacing pipes cannot solve any of these problems.

The first task is to identify the split between physical and commercial losses, because the two failures cost very different amounts to fix. A utility that spends a hundred million dollars replacing mains when two-thirds of its losses are commercial will recover very little water. The International Water Association’s water balance, the framework described below, exists to prevent that mistake. World Bank guidance treats it as the starting point for any loss-reduction strategy.

Where the water goes: the standard water balanceSystem input100%Authorised use58%Water losses42%Billed authorised use 55%Real losses 30%Billed authorised use 55%Unbilled authorised use 3%Apparent losses 12%Real losses 30%Revenue water55%Non-revenue water45%

Interactive: choose a step, or use the arrows, to change the figure

Step 1 of 4

Everything the utility puts into its network, metered at the works. It is the starting point for the water balance.

The first split. Some of the water is used with the utility’s knowledge; the rest is lost, physically or on paper.

Billed authorised use is the only part that generates revenue. Unbilled authorised use is legitimate but free: mosques, fire-fighting, street cleaning. Apparent losses are water that is delivered but not paid for. Real losses are physical leakage from mains, connections and tanks.

Non-revenue water is the last three components taken together, 45% in this illustration. Only the last of them requires excavation.

Notes

Structure follows the International Water Association’s standard water balance, which a growing number of countries use as their reporting standard. The percentages illustrate a high-loss network rather than any single utility, and every band is drawn at its true share, which is why the two thinnest are named in the key rather than labelled in place.

At three in the morning, most of the water still flowing is leakage.

A straightforward method of measuring leakage in a district relies on readings taken at night, when most residents are asleep. The utility takes a defined section of the network (in UK cities typically 500 to 3,000 properties, according to IWA guidance) and closes valves on its boundary so that all water enters through metered inlets, often just one. This is a district metered area, a core technique of modern leakage control. Flow meters on the inlets record continuously. The utility then examines the reading at three in the morning.

At three in the morning, almost nobody is using water. Legitimate night-time consumption in a residential district is small and reasonably predictable: some toilet use, a small number of night-shift workers and some commercial premises. If the meter shows that 26 cubic metres an hour are still flowing into the district, while legitimate night-time demand is 8, the remaining 18 are leaking into the ground. Leakage continues during the day, unlike demand. If that rate held all day it would come to about 158,000 cubic metres a year. In practice leakage falls as daytime pressure falls, so utilities convert the night figure with a night-day factor rather than multiplying by 24.

020406000:0004:0008:0012:0016:0020:0024:00Flow into one district over 24 hours, cubic metres per hourFlow into the districtDemand rises with the morning and evening peaks02:00–04:0026 m³/h still flowing inAt three in the morning almost nobody is using water, yet the flow does not stopLegitimate night use, about 8 m³/h18 m³/h lost to leakageMost of the flow at that hour is leakageBefore repairAfter repairLeakage runs around the clock, at a rate that varies with pressure

Interactive: choose a step, or use the arrows, to change the figure

Step 1 of 4

Flow into one district over 24 hours, rising with the morning and evening peaks as residents rise and return home.

Between two and four in the morning demand almost stops. The flow into the district does not.

Once the legitimate night use of a residential district, which is small and predictable, is subtracted, the remainder is leakage.

Once the leaks are repaired, the whole curve falls at every hour of the day, which is why the night reading is so valuable.

Notes

Illustrative profile for a district metered area of roughly 1,500 connections; the repaired curve is drawn with a constant reduction for simplicity, although leakage varies with pressure over the day. The technique is standard: isolate a district, meter what goes in, and read the flow at the hour when almost nobody is using water.

Minimum night flow shows how much water a district is losing. It does not show where the leak is. Locating the leak is a separate problem, and the past decade has changed how utilities tackle it.

A crew working in an open trench in a city street
The final stage of a leak repair. All the work before this point serves to ensure that the crew excavates in the right place.

A pressurised leak makes a noise, and the pipe carries it.

Water forced through a crack makes the pipe wall vibrate, and that vibration travels along the pipe, particularly well along metal. The classic tools are noise loggers, correlators and ground microphones. Noise loggers are sensors fixed to valves or hydrants and left in place to record the sound of the network, often overnight.

Two sensors placed on either side of a suspected leak can do more than detect the sound. The same sound reaches each sensor at a slightly different time. If the speed of sound through that pipe material is known, the difference in arrival time reveals the leak’s distance from the sensors. The method needs good transmission of noise along the pipe, but where it works it can place a leak to within about a metre per 100 metres of pipe, according to the US EPA, so the crew can dig in one place.

The most recent addition is satellite-based. According to its supplier, radar from a satellite penetrates the ground, and an algorithm tuned to treated drinking water flags places where water may be escaping. Its supplier says it can detect leaks as small as half a litre a minute. Commercial services now sell utilities a map of suspected leaks across an entire city, reducing a large network to a list of points worth investigating. The technology does not find the leak itself. It indicates which streets the crews should survey.

Before any excavation, there is the valve.

Before anyone digs, pressure management offers a relatively cheap intervention that World Bank guidance calls an often underestimated option. Leakage is a function of pressure. Increasing the pressure makes every existing hole pass more water, and some leak paths, such as splits in plastic pipe, also open wider under load. For a fixed hole, flow rises only with the square root of pressure. Real networks are usually much more sensitive than that, which is why practitioners use the leakage exponent rather than a simple ratio. In practical terms, cutting excess pressure by a third can cut leakage by rather more than a third.

Many networks are over-pressurised for much of the day. They are designed for the morning peak and for the highest point in the zone. At two in the morning, at the bottom of the hill, the pipes can therefore be carrying far more pressure, or head, than anyone needs. A pressure-reducing valve with a controller that lowers the setting overnight addresses that. It also reduces bursts. UK data show mains burst frequency rising rapidly once pressure exceeds about 35 to 40 metres of head.

Where a utility can buy its next cubic metre, dearest firstNew seawater desalinationabout $0.37 to $1.40 a cubic metre at the plantTreated wastewater reusea new plant, but no intake and no brineMetering and billing repairno excavationActive leakage controldistrict metering, acoustic survey, repair crewsPressure managementa valve and a controller; losses fall immediately
Notes

An order, not a price list. Only the desalination figure is a published number, and the cost of saved water depends entirely on the existing condition of the network. The low-cost options are also exhausted well before the leakage is. What the ladder shows is that the bottom three need no new plant, no new power and no new brine.

Desalination is the published benchmark at the top of that ladder. Dubai’s Hassyan plant set a record tariff of US$0.277 a cubic metre in 2020, but that bid was never built at that price: the 180 MIGD plant DEWA contracted in October 2023 is priced at US$0.365. World Bank data put typical seawater plant costs at roughly US$1 to US$1.40, depending on the sea.

A bank of ageing water meters on the outside wall of a building
A mechanical meter is a small turbine, and small turbines under-register at low flows. The error grows as the meter ages, and the failure is silent.

A meter that under-registers fails silently, and against the utility.

In much of the region, a large part of the problem is not underground. It is in the meter, the ledger and enforcement. Small turbines under-register at low flows, precisely the flows produced by a rooftop tank as its float valve closes. The error grows as the meter ages. Under intermittent supply, Jordan’s own loss-reduction policy expects meters to under-register within two years. The failure goes unnoticed because it is silent, and its cost falls on the utility.

A further share of water is simply taken without authorisation. Theft of water in various forms is counted as a commercial loss. Jordan’s campaigns against illegal wells and water-line violations saved 31.5 million cubic metres between January and early November 2025, but they are enforcement campaigns directed at a structural condition.

Dubai reported 4.4% losses in 2025. The MENA region’s conditions are not the obstacle.

Comparing utilities on non-revenue water is more difficult than it appears. Countries measure it differently, publish it selectively and report it as a percentage. That measure flatters any utility whose customers use a lot of water, because the denominator is larger. For physical losses, practitioners therefore prefer litres per connection per day, read with supply time and pressure. The percentages still show something real, however, because the differences between them are far too wide to be explained by definitions alone.

Share of water put into the network that is never billedNational or utility-level estimates; definitions and years differSaudi 2030 target: 15%Jordan 2040 target: 25%Jordan (2022)50%Lebanon (2024)50%Algeria (2004)40%Saudi Arabia (2025)33%Tunisia (2025)25%Morocco, physical (2023)24%FOR COMPARISONPhnom Penh (2008)6%Dubai (2025)4.4%
Notes

Jordan: Central NRW Unit figures for 2022, via the EU-funded WES programme. Lebanon: Ministry of Energy and Water national estimate in its 2024 to 2035 water strategy, which excludes water billed but not collected. Algeria (distribution losses, 2004) and Morocco (physical water losses in distribution networks): World Bank. Saudi Arabia: water losses in 2025, Ministry of Environment, Water and Agriculture via Sharakat. Tunisia: Alaa Marzouki of the Tunisian Water Observatory, as reported by Carnegie. Dubai is DEWA’s reported network loss for 2025; Phnom Penh is the widely cited post-reform figure, since reported at about 8.75% (2023). These are not measured on identical definitions, so the bands are more meaningful than the decimals.

Two things stand out. The first is that the Gulf has already shown that low losses are possible in the climate of the MENA region. DEWA reported losses of 4.4% in 2025. Qatar’s utility, Kahramaa, said in May 2026 that technical losses in its network remain below 4.5%; the country’s official statistics put real losses at 6% and total losses at 19% in 2023. Low loss rates are achievable in the region.

The second is that, outside the Gulf, some of the most water-scarce countries also report the highest losses. The reasons are the subject of the next chapter.

A desalination plant is a visible project that a minister can inaugurate.

The technology described here has existed for decades and is well understood. The MENA region does not lose so much water because its engineers do not know how to find leaks.

The first is one of the most damaging factors: intermittent supply. When a utility cannot meet demand, it rations water through rotation. Jordan’s utilities have been pushed on to intermittent supply across the country. Xinhua reported that Amman households typically receive piped water two days a week; one eastern Amman resident said his neighbourhood received water once a week. Rationing then makes the losses worse in three separate ways. Switching a network on and off damages it. In Limassol, Cyprus, two years of rationing caused additional pipe breaks and left leakage higher for years afterwards. Households respond by installing rooftop tanks, which fill through float valves at flows too low for many meters to register. An intermittent network also cannot be measured properly, because a district without water at night has no minimum night flow. The utility loses its instrument at the same moment that it loses control.

The second is finance. Tariffs across much of the region are set well below the cost of supply. On World Bank figures, the price charged covers about 35 percent of the cost of producing conventional water. A utility that recovers only a fraction of its costs cannot fund a leakage programme, replace its meter fleet or pay enough to retain the people who know where the valves are. Its losses rise and its revenue falls further.

There is also a political consideration. Reducing non-revenue water offers no opening ceremony: twelve thousand replaced service connections and a reprogrammed pressure-reducing valve do not lend themselves to publicity.

Phnom Penh reduced its losses from 72% to 6%, and pipe replacement was only part of the reform.

The most instructive counter-example lies outside the MENA region. In 1993, the water utility of Phnom Penh was losing 72% of what it produced, reached only a fifth of the city, supplied water for about ten hours a day and barely covered half its operating costs. Fifteen years later, it was losing 6%, covering 90% of its area around the clock, collecting on 99.9% of its bills and charging tariffs set for full cost recovery. Losses have since settled at about 8.75% (2023).

In the Asian Development Bank’s account, the first change was to management. Corrupt staff, including employees who installed connections illegally, were removed. A 1994 survey found 13,722 connections missing from the utility’s records, allowing the records to be corrected. Every connection was metered. A 1996 decree gave the utility administrative and financial autonomy, so that the additional revenue stayed in the network. Pipe replacement ran alongside these reforms, from 1993 to 2001.

  • 1993

    The starting point

    The utility loses 72% of what it produces, reaches a fifth of the city, supplies water about ten hours a day and covers barely half its operating costs.

  • 1994

    Correcting the records

    A survey finds 13,722 connections missing from the utility’s records. Staff who had installed connections illegally are removed.

  • 1996

    Autonomy

    A decree gives the utility administrative and financial autonomy, so that revenue it raises stays in the network.

  • 2008

    The result

    Losses are down to 6%, coverage is 90% of the city around the clock, collection runs at 99.9%, and tariffs are set for full cost recovery.

  • since

    Sustaining the gains

    Losses were about 8.75% in 2023, which is what maintaining the position looks like.

For the MENA region, the potential gain is straightforward to estimate. Domestic water withdrawals across the Arab states alone came to about 31 billion cubic metres in 2022. If losses on that water averaged around 40% and were brought down to 25%, which is Jordan’s own 2040 target rather than an unrealistic assumption, the change would free on the order of four to five billion cubic metres a year. That is more than a quarter of the region’s installed desalination capacity of about 45 million cubic metres a day, and it would require no new intake, no new membrane, no new power station and no additional brine returned to the Gulf.

It would, however, require utilities to be allowed to charge something closer to what water costs, keep the proceeds, and meter and bill customers they currently do not. Those are political decisions rather than engineering decisions, and none of the region’s utilities can take them alone. Until those decisions are taken, the region will continue to buy its next cubic metre from the sea while treated water already in its pipes leaks beneath its streets.

Images: water-main valves © Rose Galloway Green; street excavation © David Klein; water meters © Godspower Abdulahi. Via Unsplash.

Sources

35 references

Loss figures are defined differently across sources, and the shares in the water balance and the night-flow profile are illustrative rather than measured.

  1. World Bank, Beyond scarcity: water security in the Middle East and North Africa, report 120105 (2017, published 2018).
  2. LDK Consultants for the EU-funded WES programme (2024), Non-revenue water policy for Jordan, including Table 2-1, Central NRW Unit figures for 2022.
  3. Ministry of Energy and Water, Towards a Sustainable Water Sector: Lebanon’s National Water Strategy 2024–2035, June 2024 (copy held by the pS-Eau library).
  4. World Bank (2023), Morocco Country Climate and Development Report, background note on water scarcity and droughts, April 2023.
  5. World Bank, World Development Indicators, renewable internal freshwater resources per capita, Jordan (ER.H2O.INTR.PC), 2021 data.
  6. US International Trade Administration, “Jordan – Environment and Water Sector”, Country Commercial Guide.
  7. FAO, “Water scarcity”, Land and Water division (archived January 2024).
  8. SUEZ, “Second largest desalination plant in the world and 445km of pipelines to supply drinking water to the cities of Amman and Aqaba”, 15 January 2025.
  9. EBRD and the Ministry of Water and Irrigation (2025), Aqaba–Amman project, environmental and social impact assessment: non-technical summary, December 2025.
  10. Jordan News Agency (Petra), “Water loss cut to 41%, exceeding target”, 24 August 2026.
  11. World Bank (2004), Seawater and Brackish Water Desalination in the Middle East, North Africa and Central Asia, annex 1: Algeria.
  12. Sharakat (Saudi Water Partnership Company), 7 Year Statement 2025–2031, March 2026, p. 20, citing the Ministry of Environment, Water and Agriculture (water losses 33% in 2025).
  13. Noura Omar, Carnegie Endowment for International Peace (Sada), “Securing Tunisia’s constitutional right to water: policy solutions”, 28 February 2025, quoting Alaa Marzouki, coordinator of the Tunisian Water Observatory.
  14. Jones, E. et al. (2019), “The state of desalination and brine production: a global outlook”, Science of the Total Environment 657, full text.
  15. Liemberger, R. and Wyatt, A. (2019), “Quantifying the global non-revenue water problem”, Water Supply 19(3), doi:10.2166/ws.2018.129 (publisher-deposited abstract; the article itself is paywalled).
  16. DEWA release carried by Zawya, “DEWA’s Hydro Insight system analyses data from more than 1.1mln smart water meters in Dubai every 15 minutes”, 7 August 2026 (water losses 4.4% in 2025).
  17. Kingdom, B., Liemberger, R. and Marin, P. (2006), The challenge of reducing non-revenue water in developing countries, World Bank Water Supply and Sanitation Sector Board Discussion Paper 8.
  18. US Environmental Protection Agency (1999), Guidance manual for conducting sanitary surveys of public water systems, EPA 815-R-99-016, April 1999.
  19. US Environmental Protection Agency (2010), Control and mitigation of drinking water losses in distribution systems, EPA 816-R-10-019, November 2010.
  20. Criminisi, A. et al. (2009), “Evaluation of the apparent losses caused by water meter under-registration in intermittent water supply”, Water Science and Technology 60(9), doi:10.2166/wst.2009.423 (abstract read via Crossref; the publisher blocks automated access).
  21. Phnom Penh Water Supply Authority, “Non-revenue water”.
  22. ILBANK (İller Bankası), Sustainable Cities Project, Non-revenue water management guideline, final, September 2022.
  23. IWA Water Loss Specialist Group, District Metered Areas: guidance notes for DMA management, version 2, March 2024.
  24. ASTERRA (formerly Utilis), “About satellite leak detection technology”. A supplier claim; no independent evaluation of the 0.5 litre-a-minute threshold was located.
  25. Lambert, A., “What do we know about pressure:leakage relationships in distribution systems?”, conference paper (third-party copy).
  26. Government of Dubai Media Office, “DEWA achieves a new world breaking record for lowest water levelised tariff of 0.277 USD per cubic metre”, 3 September 2020.
  27. DEWA press release via Dubai Financial Market, “DEWA and ACWA Power sign water purchase agreement and shareholder agreement for phase 1 of the world’s largest solar energy-powered desalination plant”, 4 October 2023.
  28. World Bank (2019), The role of desalination in an increasingly water-scarce world, Water Global Practice technical paper.
  29. Jordan News, “Water Ministry: anti-violation campaign saves 31.5 million cubic meters in 2025”, 13 November 2025.
  30. The Peninsula, “Qatar achieves 35% water reserve surplus”, 17 May 2026, reporting Kahramaa figures.
  31. National Planning Council (Qatar), Qatar Water Statistics Report 2023, November 2024 (total water losses 19%, real losses 6%, 2023).
  32. Xinhua, “Jordan battles severe water crisis with managed distribution, strategic projects”, 20 September 2025.
  33. Charalambous, B., “The effect of intermittent supply on water distribution networks”, Water Board of Lemesos case study, first presented at the IWA Efficient conference in Amman (2011) and updated in 2015.
  34. Asian Development Bank, “Country water action: Phnom Penh Water Supply Authority: internal reforms fuel performance upgrade”, 30 September 2008.
  35. World Bank, World Development Indicators, Arab World aggregate, 2022: total freshwater withdrawals (ER.H2O.FWTL.K3) and domestic share of withdrawals (ER.H2O.FWDM.ZS). Domestic volume calculated by MENA Water Review.

Every figure and claim in this story rests on the references above. The stories list them here rather than marking them in the text; the country reports and hubs keep their inline markers.