Silvan Dam and Irrigation Tunnels

Dam and irrigation tunnels, 7 km3 reservoir; Silvan irrigation tunnel 13,236 m long with a 10 m internal diameter and 212 m3/s capacity; 235,000 ha irrigation command in Turkey.

Under construction

The record

Country
Turkey
Location
Silvan, Diyarbakır
Coordinates
38.293, 41.021
Technology
Dam and irrigation tunnels
Capacity
7 km3 reservoir; Silvan irrigation tunnel 13,236 m long with a 10 m internal diameter and 212 m3/s capacity; 235,000 ha irrigation command
Capital cost
TRY 255 bn total project cost of the Silvan project (DSI, April 2025), converted at TRY 39.45 per US$ (World Bank official exchange rate, 2025 average); the minister put the investment at about TRY 360 bn in August 2026, not converted because 2026 has no full-year rate
Stage
Under construction
Owner or client
General Directorate of State Hydraulic Works (DSI)
Contractor
—
Operator
—
Finance
—
Award or start year
2012
Commissioned
—

Record last checked 2026-10-12.

History

Sources

8 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. DSI, Dev kostebek en buyuk tunel icin donmeye basladi, 17 April 2025. dsi.gov.tr.
  2. States that the Silvan dam will hold 7 billion m3 and will be the second largest irrigation dam in GAP after the Ataturk dam, that the Silvan project comprises 31 components including 8 dams and 23 irrigation facilities with Ambar, Kurucay, Baslar and Pamukcay complete, that the Silvan irrigation tunnel will be 13,236 m long with an 11.2 m excavated and 10 m internal diameter and a 212 m3/s capacity, that tunnel boring began on 17 April 2025, that total project cost reaches 255 billion lira, and that 2,350,000 dekar (235,000 ha) will be irrigated.
  3. DSI 10th Regional Directorate, Silvan Sulama Tunelinde kazi calismalari, 22 April 2025. bolge10.dsi.gov.tr.
  4. (server TLS is intermittent, returns 200 on retry).
  5. Haber Meydan, Silvan Projesi icin kritik tarih belli oldu, 13 August 2026. habermeydan.com.
  6. Reports Minister Ibrahim Yumakli saying the dam body is complete, impoundment is targeted for September 2027, the Babakaya tunnel tubes for March 2027 and the Silvan tunnel for 2027, with the investment now about 360 billion lira.
  7. Hurriyet Daily News, Work begins on 6 billion Turkish Lira irrigation dam in Silvan, May 2012. hurriyetdailynews.com.
  8. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

Dates the construction ceremony to 3 May 2012 and gives a 174.5 m dam height.