Al-Haier ISTP

Wastewater treatment, 200,000 m3/day in Saudi Arabia.

Under construction

The record

Country
Saudi Arabia
Location
Riyadh (Al Ha'ir)
Coordinates
24.350, 46.910
Technology
Wastewater treatment
Capacity
200,000 m3/day
Capital cost
—
Stage
Under construction
Owner or client
Sharakat (Saudi Water Partnership Company)
Developer
Miahona / BESIX / Marafiq
Contractor
—
Operator
—
Finance
Project finance
Award or start year
2026
Commissioned
—

Record last checked 2026-09-20.

History

Sources

5 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. Sharakat, 7 Year Statement 2025-2031 (March 2026), Tables 3, 7 and 8. sharakat.com.sa.
  2. Sharakat company portfolio. sharakat.com.sa.
  3. Coordinates locate the Al Ha'ir treatment area south-east of Riyadh, from the OpenStreetMap wastewater plant named محطة الحائر, and are given to two decimals because the independent plant's own footprint is not published.
  4. Saudi Water Partnership Company, financial close of Al Haer Independent Sewage Treatment Plant, 7 February 2025. sharakat.com.sa.
  5. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

Developed by a consortium of Miahona, BESIX and Marafiq; commercial operation in the fourth quarter of 2026.