Tan-Tan Desalination

Brackish water RO, 12,100 m3/day, about 4.4 million m3/year; the 2014 phase is 9,000 m3/day in Morocco.

Operational

The record

Country
Morocco
Location
Tan-Tan
Coordinates
—
Technology
Brackish water RO
Capacity
12,100 m3/day, about 4.4 million m3/year; the 2014 phase is 9,000 m3/day
Capital cost
—
Stage
Operational
Owner or client
ONEE
Contractor
—
Operator
ONEE
Finance
—
Award or start year
2003
Commissioned
2014

Record last checked 2026-09-18.

History

Sources

3 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. ONEE, Experience de l'ONEE en matiere de dessalement d'eau, IME webinar (Jun 2021). remoc.org.
  2. ONEE's inventory gives Tan-Tan brackish water treatment an operational capacity of 12,100 m3/day commissioned in 2003 and 2014; the fiche technique for the 2014 phase gives 9,000 m3/day by reverse osmosis on brackish water at 15 to 20 g/l TDS on grid power, and a further 4,320 m3/day was out to consultation in 2021. Policy Center for the New South, Desalinisation, barrages et autoroutes de l'eau, PP-19/25 (May 2025). policycenter.ma.
  3. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

Table 2 plans a 47.20 Mm3/year seawater scheme at Tan-Tan for 2027 to 2040, including 9 Mm3/year for green hydrogen.