Bandar Abbas Desalination

Seawater RO, 100,000 m3/day (ten units of 10,000 m3/day) in Iran.

Operational

The record

Country
Iran
Location
Bandar Abbas
Coordinates
27.200, 56.300
Technology
Seawater RO
Capacity
100,000 m3/day (ten units of 10,000 m3/day)
Capital cost
cost not disclosed (no total or US$ figure in the Farab sources)
Stage
Operational
Owner or client
Hormozgan Regional Water Co. (offtaker)
Developer
Farab / Tana Energy Management / TIV Energy / Machine Sazi Vijeh
Contractor
Shaya Co., joint venture of Farab, Tana Energy Management, TIV Energy and Machine Sazi Vijeh
Operator
Shaya Co. under a build, own, operate contract
Finance
Domestic
Award or start year
—
Commissioned
2018-12

Record last checked 2026-10-16.

History

Sources

5 references

Every field in the record above is taken from the references below. A field that none of them confirms prints as a dash.

  1. Farab, Bandar Abbas sea water reverse osmosis desalination plant (project page). farab.com.
  2. Farab, Inaugurating the second phase of the largest desalination plant of the country in Bandar Abbas, 18 July 2020. farab.com.
  3. Farab, Inaugurating phase one of the largest desalination plant of the country in Bandar Abbas, 17 Dec 2018. farab.com.
  4. Phase one, 20,000 m3/day, inaugurated in December 2018. Farab, The third and final phase of Bandar Abbas desalination plant was inaugurated, 2 May 2021. farab.com.
  5. MENA Water Review major projects register and PPP pipeline — compiled from procurer publications, development-bank project pages and trade reporting; each record names its source.

60,000 m3/day inaugurated on 29 April 2021, completing 100,000 m3/day. The year the build-own-operate contract was signed is not given in the sources consulted (Farab, Tana Energy, Mehr, Tejarat News), so the award or start year is left blank; the earlier 2023 entry was later than the plant's commissioning.