Case study
As-Samra: treating Amman’s wastewater as a water source
The plant that treats the wastewater of Amman and Zarqa for irrigation in the Jordan Valley. It was Jordan’s first private-sector co-financed build-operate-transfer project. A Millennium Challenge Corporation grant cut the capital cost of the phase II expansion and made it financially viable, while the finance model was designed to keep treatment tariffs affordable.
- Serves
- Greater Amman and Zarqa1
- Capacity, phase I
- 267,000 m³/day from April 20081
- Capacity, phase II
- 365,000 m³/day1
- Structure
- 25-year build-operate-transfer2
- Sponsors
- Suez Environnement, Infilco Degremont and Morganti1
- Grant funding
- USAID for phase I, the US Millennium Challenge Corporation for phase II1
Context
Jordan cannot afford to use water once. Agriculture consumes about half of the country’s water, more than any other sector.3 The Jordan Valley’s irrigated farming sits downstream of the country’s densest urban area, and the terrain lets Amman’s wastewater reach it cheaply.2
That makes treated effluent from Amman a water source rather than a disposal problem. It grows with the city rather than with the rainfall.2
The design
As-Samra treats the wastewater of Greater Amman and Zarqa. It discharges through Wadi Dhuleil to the Zarqa River, and the water collects in the King Talal reservoir to supply irrigation in the Jordan Valley.1 The Ministry of Water and Irrigation is the public counterparty.2
It was delivered under a 25-year build-operate-transfer concession, signed in 2003 and extended in 2012, rather than by direct public works.2 The sponsors are Suez Environnement, Infilco Degremont and Morganti, and the plant is run by a dedicated operating company. MIGA signed a guarantee for the first phase in May 2006, and the plant entered commercial operation in April 2008 at 267,000 cubic metres a day.1
The expansion followed. Construction began in the second half of 2012, taking capacity to 365,000 cubic metres a day and raising sludge treatment capacity by 80 per cent.1 MIGA announced guarantees of US$13.1 million for the sponsors’ equity in July 2013, covering the existing plant and the expansion against breach of contract for up to 20 years.4 The expanded plant was inaugurated in October 2015.2
What worked
The reuse is real and at scale. Nearly 68 per cent of the wastewater flowing across Jordan passed through As-Samra in 2021, and the plant produced about 130 million cubic metres that year, discharged into Wadi Zarqa and flowing into the King Talal Dam and then King Abdullah Dam for irrigation in the Jordan Valley.5
The finance is the underrated part. Phase I was supported by USAID grant funds and phase II by the Millennium Challenge Corporation.1 MCC put US$93 million into the US$275 million expansion, alongside about US$148 million of bank debt, US$8.6 million of sponsor equity and at least US$19.8 million from the government. Lenders and sponsors covered more than half of the cost, and the operator was required to operate and maintain the facility for 25 years.2 6 The finance model did not rely to any significant degree on charges to wastewater-generating households or farmers. The government paid the operator about US$0.17 a cubic metre for treatment in 2014, while the MCC grant reduced capital costs and helped keep treatment tariffs low.2
What did not, or is unresolved
Reuse of this kind is bounded twice over, by what the city produces and by what the receiving system can carry. It does not close Jordan’s deficit, it slows the rate at which the deficit widens. MCC’s evaluation put the fresh water freed for urban use at 4 to 6 million cubic metres a year, about 0.5 per cent of national use.6
Quality management is permanent work rather than a solved problem. The same evaluation found that farmers reported declining irrigation water quality compared with controls, though farm revenues did not fall. The area irrigated with treated wastewater also fell during the compact, which MCC links to a wider decline in cultivated area in the Jordan Valley.6
In 2018 the EBRD and the EU announced financing to add 100,000 cubic metres a day at As-Samra.7 The EBRD loan announced in 2021, €30 million with a €30 million EU grant, finances a new plant at Al Ghabawi, which the minister said would reduce the biological load at As-Samra.8 In July 2026 the ministry signed a US$28 million expansion of As-Samra, backed by the US government, with the operating company. It is scheduled for completion in 2028, and no added capacity was stated.9
What it means for the next one
Wastewater is a supply that grows with urbanisation.2
The lesson from As-Samra is institutional rather than technical. The value is captured when the effluent has a named downstream user and a delivery route to reach them. It is lost when a plant is built to a discharge standard with nobody waiting at the other end. Jordan built the route first, through the King Talal reservoir that supports most Jordan Valley farming, which is why the plant counts as supply rather than sanitation.2
Sources
9 references
MIGA gives the phase II capacity as 365,000 m³ a day and the IWMI case study as 364,000; MIGA’s figure is used. Neither the 2018 announcement nor the 2021 EBRD release says whether the planned As-Samra expansion was replaced by the Al Ghabawi plant.
- MIGA, As-Samra wastewater treatment expansion project, board 20 June 2013.
- Drechsel, P., Danso, G. and Hanjra, M. (2018), “Viability gap funding: the As-Samra wastewater treatment plant, Jordan”, in Resource Recovery from Waste, via CGSpace.
- U.S. International Trade Administration, Jordan Country Commercial Guide: Environment and Water Sector, last published 26 February 2026.
- MIGA, “MIGA Backs Wastewater Treatment Plant in Jordan”, press release, 23 July 2013.
- Ministry of Water and Irrigation, National Water Strategy 2023–2040, 2023, PDF pp. 60 and 62 (2021 figures).
- Millennium Challenge Corporation, Closed Compact Report: Jordan Compact, As-Samra Wastewater Treatment Plant Expansion Project, September 2018.
- Smart Water Magazine, “Jordan’s Samra wastewater treatment plant to be expanded”, 17 December 2018.
- EBRD, “EBRD and EU upgrade wastewater services in Jordan”, 29 November 2021.
- Petra, “Jordan Signs $28M Deal to Expand As-Samra Wastewater Treatment Plant”, 29 July 2026.
Numbered references are linked from the superscript markers in the text. Figures without a marker come from the sources above as compiled in the site methodology.